Speaking to the 'Tiser Kemp said; "The project is developing quickly now and you will see big changes week to week. We're in the early stages of steel erection and that will run for 16 weeks and finish at the end of January."
"Then, early in the new year, we'll start with the roof and the floors and kit out the West Stand and get the whole thing ready for the July completion date. I'm never ahead of schedule, I'll never admit to that, but it's going to plan and all the sub-contractors are lined up for the following trades."
"We've had a lot of material imported to lift the site so it is out of the flood plane and the weather has helped. It's been good up to now and we're hoping for a nice, mild winter to help us along. Whatever it throws at us, we will get there." he added.